Does anyone know if Project 2003 utilizes Equipment
Resources? I am working on a huge project where I need
this option to create a succesful model.

If it does support it will it differentiate between that
and a Work Resource. For example I have a tool and three
mechanics to do the work. But I do not want the task
started until BOTH the tool and mechanic available.

With Project 2002 I have tried to use work resources for
both the tool and equipment but the task begins as soon
as one or the other is available which creates a bad plan.

HELP!!!! Please email me at [email protected] or
[email protected]

Kevin
 