Hi everybody !
I've got 2 problems with Project Pro 2002 and Server.
1) Resource inputs and accepts time progress of his tasks and on PWA and
gets info saying that everything is sent to PM for accepting. PM receives
only part of information concerning 10 of 20 tasks, and what more strange -
these 10 have bad time progress signed.
On the next day resource visits his PWA and can notice that many of tasks he
sent yesterday are still not touched and has to input progress again. And
the same situation repeats day after day, only tasks are different. What can
cause the problem ?
2) On Windows XP machines, with MS Office 2003 and Project Pro 2002
installed users cannot do "drag-and-drop" operation between Project and
Excel cells. Project crashes at once in random moments espacially during
copying whole columns or cells.
Users of Office2000 do not have such problems.
Any help welcome
Mike
I've got 2 problems with Project Pro 2002 and Server.
1) Resource inputs and accepts time progress of his tasks and on PWA and
gets info saying that everything is sent to PM for accepting. PM receives
only part of information concerning 10 of 20 tasks, and what more strange -
these 10 have bad time progress signed.
On the next day resource visits his PWA and can notice that many of tasks he
sent yesterday are still not touched and has to input progress again. And
the same situation repeats day after day, only tasks are different. What can
cause the problem ?
2) On Windows XP machines, with MS Office 2003 and Project Pro 2002
installed users cannot do "drag-and-drop" operation between Project and
Excel cells. Project crashes at once in random moments espacially during
copying whole columns or cells.
Users of Office2000 do not have such problems.
Any help welcome
Mike