S
SteveB
I want a task with a work column that has an 40 hrs (my estimate). I want to
update the actual work to be 30 hours. I want the % work complete to be 100%
and see the variance of 10 hours. In either case, the duration should remain
20 days.
In other words - I estimated 40 hours of work but was 100% complete with
only 30 hours of actual work but still took the whole 20 days.
Is this possible and how would I set it up?
Thank you.
update the actual work to be 30 hours. I want the % work complete to be 100%
and see the variance of 10 hours. In either case, the duration should remain
20 days.
In other words - I estimated 40 hours of work but was 100% complete with
only 30 hours of actual work but still took the whole 20 days.
Is this possible and how would I set it up?
Thank you.