Doug
I have a master schedule that uses two companies as their main contractors.
Each contractor is given a FY budget that can span 3yrs (FY05,06,07)
In some instances, both contractors work on the same activity and there may
be up to 2 FY of budget for each contractor on that one activity. Also, the
costs associated with an activity are fixed.
I would like to know if there are any "best demonstrated practices" for
doing an analysis of EV for a given FY by each contractor. Right now I have
the activity broken down by FY (ie Build widget FY06, Build widget FY07) I
know this is an ugly way to schedule activities. I have thought about
creating Generic Resources based on FY for each contractor, but this isn't
truly accomplishing my goal.
Thanks for any help!!
Each contractor is given a FY budget that can span 3yrs (FY05,06,07)
In some instances, both contractors work on the same activity and there may
be up to 2 FY of budget for each contractor on that one activity. Also, the
costs associated with an activity are fixed.
I would like to know if there are any "best demonstrated practices" for
doing an analysis of EV for a given FY by each contractor. Right now I have
the activity broken down by FY (ie Build widget FY06, Build widget FY07) I
know this is an ugly way to schedule activities. I have thought about
creating Generic Resources based on FY for each contractor, but this isn't
truly accomplishing my goal.
Thanks for any help!!