D
DWeb
Hello! I am looking for suggestions for how to approach the following
scenario.
I have a list of issues that represent work requests. Each of these issues
may or may not spawn one or more change requests (CRs) that will always be
associated with the parent issue. I currently have high-level work estimates
for each issue, broken out by phase (i.e. Requirements, Design, Build, Test,
Deploy).
I would like to track work/schedule/assigned resources for each issue (and
any associated CRs) and be able to show that the CRs roll-up to a given
issue. As CRs come up, I would like to be able to add the CR (as a subtask
of the issue if that makes sense) and associate a portion of the "budget" for
that issue to the CR, leaving the remaining budget with the issue.
Similarly, if another CR is added, I would like to be able to carve out part
or all of the remaining issue budget and associate it with the CR. Each CR
would have the same phases as the original issue. Resources can be assigned
to the issue, CR, or both.
So if issue #1 had 10 hours each for Requirements, Build, Test, Deploy, if I
add CR #1-1 with those same phases allotted at 5 hours each, then issue #1
would show 5 hours of budget for each phase. If I added 2 such CRs (#1-1
and #1-2) at 5 hours per phase, then the original issue would show 0 hours
remaining for each phase.
Another component of this scenario is that I would like to be able to
quickly see that a group of issues/CRs and the associated tasks are related.
I thought about using a custom field to hold the parent issue #, but realize
that may make for the same value repeated in multiple rows, which I guess can
be automated by macros, but I'm open to thoughts on this as well.
Sorry for the long-winded description - I hope it made sense. Please
respond with any suggestions or guidance. I do appreciate it.
scenario.
I have a list of issues that represent work requests. Each of these issues
may or may not spawn one or more change requests (CRs) that will always be
associated with the parent issue. I currently have high-level work estimates
for each issue, broken out by phase (i.e. Requirements, Design, Build, Test,
Deploy).
I would like to track work/schedule/assigned resources for each issue (and
any associated CRs) and be able to show that the CRs roll-up to a given
issue. As CRs come up, I would like to be able to add the CR (as a subtask
of the issue if that makes sense) and associate a portion of the "budget" for
that issue to the CR, leaving the remaining budget with the issue.
Similarly, if another CR is added, I would like to be able to carve out part
or all of the remaining issue budget and associate it with the CR. Each CR
would have the same phases as the original issue. Resources can be assigned
to the issue, CR, or both.
So if issue #1 had 10 hours each for Requirements, Build, Test, Deploy, if I
add CR #1-1 with those same phases allotted at 5 hours each, then issue #1
would show 5 hours of budget for each phase. If I added 2 such CRs (#1-1
and #1-2) at 5 hours per phase, then the original issue would show 0 hours
remaining for each phase.
Another component of this scenario is that I would like to be able to
quickly see that a group of issues/CRs and the associated tasks are related.
I thought about using a custom field to hold the parent issue #, but realize
that may make for the same value repeated in multiple rows, which I guess can
be automated by macros, but I'm open to thoughts on this as well.
Sorry for the long-winded description - I hope it made sense. Please
respond with any suggestions or guidance. I do appreciate it.