B
Brian Ho
I have a budget cost break down by tasks that I would like to associate the
labor cost to the budget cost so that I can see how much is used against the
budget task.
For example:
Project is Microsoft Server 2008 upgrade. The overall budget is $200K. The
break of of $200K is:
1. Labor for IT team to work on server hardware preparation - $50,000.
2. Labor for IT team to work on software migration - $50,000.
3. Labor for programming team to migrate applications to new server - $60,000.
4. Labor for QA team to test the new server and applications - $30,000.
5. Labor for UAT to implement server 2008 to production - $10,000.
I set up above 5 budget resources as cost and check budget check box on the
resource information under resource sheet. I assign these budget resources
to the Project Summary Task on row 0. I set baseline for the project before
assigning labor resources to these tasks. Note: I am not sure if this is
right by setting the baseline before assigning labor resources to the tasks
or should I set baseline AFTER assigning labor resources to the tasks.
Now, I assign the labor resources to each task by adding IT team member to
the task resource name as they begin to work on these tasks. Each one of
them have their own stardard labor rate assigned. As they work on the tasks,
I want to see how much labor cost is used against the budget cost of the task
to ensure we are within the budget. How and where can I see the over or
under budget by task?
Thanks,
Brian
labor cost to the budget cost so that I can see how much is used against the
budget task.
For example:
Project is Microsoft Server 2008 upgrade. The overall budget is $200K. The
break of of $200K is:
1. Labor for IT team to work on server hardware preparation - $50,000.
2. Labor for IT team to work on software migration - $50,000.
3. Labor for programming team to migrate applications to new server - $60,000.
4. Labor for QA team to test the new server and applications - $30,000.
5. Labor for UAT to implement server 2008 to production - $10,000.
I set up above 5 budget resources as cost and check budget check box on the
resource information under resource sheet. I assign these budget resources
to the Project Summary Task on row 0. I set baseline for the project before
assigning labor resources to these tasks. Note: I am not sure if this is
right by setting the baseline before assigning labor resources to the tasks
or should I set baseline AFTER assigning labor resources to the tasks.
Now, I assign the labor resources to each task by adding IT team member to
the task resource name as they begin to work on these tasks. Each one of
them have their own stardard labor rate assigned. As they work on the tasks,
I want to see how much labor cost is used against the budget cost of the task
to ensure we are within the budget. How and where can I see the over or
under budget by task?
Thanks,
Brian