lindforsw
I added Buget-Labor to the Resource sheet and selected budget and can work
for the type. I then assigned the Budget labor to the project summary task.
When I went to review the Resource usage to view the budget, it was zero.
I followed the microsoft creating a buget guide step by step. I have a
resource (non Budget) setup with a hourly cost (work) that totals over 5000
dollars so there is data for a projection. What am I missing?