P
Pratta
I assigned a cost resource that is a budget resource to a project summary
task, and entered a budget amount in the Res Usage or Task Usage view.
Looked ok.
However, when progressing the project with actuals the budget does not get
utilised.
Nor does the project summary task show progress after the budget resource
is assigned.
Using MS Project 2007 Std.
Am I missing something?
Would appreciate any insights.
Thanks...............Pratta
task, and entered a budget amount in the Res Usage or Task Usage view.
Looked ok.
However, when progressing the project with actuals the budget does not get
utilised.
Nor does the project summary task show progress after the budget resource
is assigned.
Using MS Project 2007 Std.
Am I missing something?
Would appreciate any insights.
Thanks...............Pratta