S
Steven
Hi
Is there a similar function to the Lotus 1-2-3 "fill by example". I've
tried the Fill option under Edit, however can't seem to get it to work with
dates. For example if I enter in 3 dates in a column (see example below), I
would then like the next 20 or so rows for that column to be filled in with
dates incrementing by one week.
e.g
31.10.2005
07.11.2005
14.11.2005
thanks in advance.
Steven
Is there a similar function to the Lotus 1-2-3 "fill by example". I've
tried the Fill option under Edit, however can't seem to get it to work with
dates. For example if I enter in 3 dates in a column (see example below), I
would then like the next 20 or so rows for that column to be filled in with
dates incrementing by one week.
e.g
31.10.2005
07.11.2005
14.11.2005
thanks in advance.
Steven