Spear
I have been trying to get a schedule to accept IF values to exclude sundays
and add one day. Example IF __ = Sunday then add 1 or if __=holiday then
add 1
This is a construction schedule which requires X amount of days between each
activity
and add one day. Example IF __ = Sunday then add 1 or if __=holiday then
add 1
This is a construction schedule which requires X amount of days between each
activity