How does the community go about tracking single use and multi use expenses in
Project. Particularly interested in ideas for travel time and cost.

Currently for multiple use fixed cost items I use a resource but this
doesn't match too well with travel where time is required too.

Looking forward to sharing ideas.
 
J

JulieS

Alan,

If you have Project 2007, you can use cost resources. In Project
2003 and earlier, about the only option was fixed costs set at the
task level.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
A

Alan S

Julie

Life saver. It looks as though there are limitless (almost :) ) options now
for tracking cost.

Thanks for you help

Alan
 
J

JulieS

Hello Alan,

Yes, the addition of the cost type resource is very helpful! Glad
to have helped and thanks for the feedback.

Julie
 