How do you simply Expand All or Collapse All Tasks?
koolkat said:How do you simply Expand All or Collapse All Tasks?
__________ Information from ESET Smart Security, version of virus
signature database 4601 (20091112) __________
The message was checked by ESET Smart Security.
http://www.eset.com
vanita said:Hi
For Collapsing all you may use 'Summary tasks' filter through Project >
Filtered for > Summary tasks.
For Expanding all similarly use the filter of 'All tasks'.
I hope it helps.
Vanita
Rod Gill said:Click the Show button on the toolbar then select the level you want to
collapse to.
--