I am struggling to create an export map to export resource information. I
have no problem creating a map for Gantt chart information and use this
regularly, but I want to be able to export information with respect to
resources and in particular the Resource Usage View.
Currently I can get the information using copy from the Resource Usage view
and paste into excel, but this is very time consuming on multiple projects.
Therefore is there any way I can map the following information in the same
format as the Resource Usage View :
Task Summary Name Resource Name Max Units Work (in days)
The in the detail against each task (on right side of screen) I need work in
days per day
Hope this makes sense and any assistance appreciated
have no problem creating a map for Gantt chart information and use this
regularly, but I want to be able to export information with respect to
resources and in particular the Resource Usage View.
Currently I can get the information using copy from the Resource Usage view
and paste into excel, but this is very time consuming on multiple projects.
Therefore is there any way I can map the following information in the same
format as the Resource Usage View :
Task Summary Name Resource Name Max Units Work (in days)
The in the detail against each task (on right side of screen) I need work in
days per day
Hope this makes sense and any assistance appreciated