Exporting Actual Work bookings from Project

N

Neil

Does anyone know how I can use VBA to get at the actual
work bookings for a resource for a task. I have some
snipets of code but they don't do the job. I also want to
be able to get the actual work data in the units of either
days or hours.

Regards
Neil
 
J

John

Neil,
Did you try the "analyze timescaled data in Excel" macro that is
available on the "Analysis" toolbar? If you use it from the Task Usage
view, you should get pretty close to what you want.

If the built-in macro doesn't do what you want, let us know, myself or
others on this newsgroup can help you generate a custom macro to
transfer your data.

John
 