exporting manpower histograms to excel

D

David

Please help. Cannot easily export week by week resource
requirements without mapping. This was much easier in
Project 2000. I need an excel spreadsheet with resource
names in column a, Dates in row 1, and numbers of each
resource required week by week
 
M

Mike Glen

Hi David,

Welcome to the Microsoft Project newsgroup :)

How did you do it in 2000, and what are you finding different in 2002?

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top