S
SBelling
Greetings:
Can anyone recommend a best practice for indicating that a
project is on hold?
We have already added a custom field with various project
status categories that reflect our SDLC including "On
Hold."
Wondering best practices to set the tasks, project dates,
resource assignments, dependencies, etc to indicate that,
for example, a proejct underway in the 1st qtr may be
paused, to resume with the same resources in Sept.
Thanks,
SBelling
Can anyone recommend a best practice for indicating that a
project is on hold?
We have already added a custom field with various project
status categories that reflect our SDLC including "On
Hold."
Wondering best practices to set the tasks, project dates,
resource assignments, dependencies, etc to indicate that,
for example, a proejct underway in the 1st qtr may be
paused, to resume with the same resources in Sept.
Thanks,
SBelling