M
Mike S.
I cannot seem to locate anything that describes the recommended way to enter
and track external costs into projects so that reporting through project or
PWS will break it out from the overall project costs.
Example1: Implementation of Exchange2003 - purchase hardware & software.
Example2: Implementation of ADS - external consultants to be used (only need
to see this as a flat rate, no need to track hourly work for these).
Using Project 2003 Pro & PWS 2003 SP1
Any general direction would be greatly appreciated.
Thanks!
Mike
and track external costs into projects so that reporting through project or
PWS will break it out from the overall project costs.
Example1: Implementation of Exchange2003 - purchase hardware & software.
Example2: Implementation of ADS - external consultants to be used (only need
to see this as a flat rate, no need to track hourly work for these).
Using Project 2003 Pro & PWS 2003 SP1
Any general direction would be greatly appreciated.
Thanks!
Mike