I have a program level schedule in Project Server 2003 with some high level
deliverables. My Program level deliverable will have multiple ghost tasks
which are summary tasks in other schedules. Those ghost tasks show %
complete but I can't get them to roll up to the deliverable or a summary task
acting as the deliverable.