In relation to the subject -Creating Dependencies Between Projects- I read
the following in the MSP Help files: "project schedule is not updated
automatically when external dependencies change" Also:
"To selectively accept changes to external predecessors, in the Task column,
select each external predecessor or successor that has changes that you want
to accept, and then click Accept".
My question is that even when the (Automatically accept new external data)
box under Tools>Options>View tab> is checked off, still the dependant task
in my project plan is updated automatically, why...? I use Project std
2007,
Any idea please, thanks in advance
In relation to the subject -Creating Dependencies Between Projects- I read
the following in the MSP Help files: "project schedule is not updated
automatically when external dependencies change" Also:
"To selectively accept changes to external predecessors, in the Task column,
select each external predecessor or successor that has changes that you want
to accept, and then click Accept".
My question is that even when the (Automatically accept new external data)
box under Tools>Options>View tab> is checked off, still the dependant task
in my project plan is updated automatically, why...? I use Project std
2007,
Any idea please, thanks in advance