Hi,
Does external link between two tasks of 2 Project belonging to 2 different
managers is possible with project server 2003 like we can do it on Project
2003 pro without the server.
Thanks a lot for your answers
 
R

Rod Gill

Yes. However, when you open a project with external links to other projects,
Project opens the other projects to get the latest dates. If you have a
slowish network, then opening a project takes a lot longer.

On some systems I've created macros to update tasks manually using a project
name and id in custom fields as this was much faster then links between
projects. Just open both projects, link between them, save both then close
and open again to see how your system responds.

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: http://www.projectvbabook.com
 