external predecessors in project center view

H

hanni

Hi,

In the project server - project center view - project view - it shows
the external predecessors. How can I delete it from project view?

Thanks,
Hanni
 
A

Andrew Lavinsky

I don't have an environment in front of me, but external tasks have a
specific identifying field in MS Priject. Doubleclick on the Gantt Chart to
get the bar styles and check which field that is. I believe it's "external."

you should be able to filter on that field in the Project Details view in
PWA.
 
B

Ben Howard

Unders Server Settings, for the view you are using, edit the Gantt Chart
Format so that it does not show External Tasks. (probably Gantt Chart (views)
or Detail Gantt (views))
 
Top