A
Armand451
Hello all,
I have a project in which the FF relationship is not working. I have read
the help and believe that the reason is because the start date for the
dependent task is in the past. However, it is important to note that I have
not set an actual start date. I guess that Project just automatically assumes
the start date as being actual since it is in the past.
Well, the problem is that when I adjust the finish date of the predecessor
to be one month past the successor's finish date, the successor's finish date
does not move. How can I over ride this?? The predecessor task has slipped
and I need the program to show that this will also cause the successor to
slip. Since a FF relationship is supposed to mean that the dependent task
cannot finish until the previous one ends, that is what I want to happen. How
do I insure that this does indeed happen?
Thanks in advance!
Jordan
I have a project in which the FF relationship is not working. I have read
the help and believe that the reason is because the start date for the
dependent task is in the past. However, it is important to note that I have
not set an actual start date. I guess that Project just automatically assumes
the start date as being actual since it is in the past.
Well, the problem is that when I adjust the finish date of the predecessor
to be one month past the successor's finish date, the successor's finish date
does not move. How can I over ride this?? The predecessor task has slipped
and I need the program to show that this will also cause the successor to
slip. Since a FF relationship is supposed to mean that the dependent task
cannot finish until the previous one ends, that is what I want to happen. How
do I insure that this does indeed happen?
Thanks in advance!
Jordan