Ok, further to previous questions I have now mapped a field in my access
database called 'resource allocation' to the 'units' field in project. In
Project I can only find 'units' under the resource tab of Task information,
also it is going in at the default 'max units' value not the value that
should be imported from the mapped field. Any idea what I am doing wrong?
Also what do I have to do with Access to set 'Task Type' to 'Fixed Duration'
and set 'Effort Driven' to No?
Thanks for the help with this!!.
Bill