Field Name

D

Diane

Actually, the question should be - if I add Text1 to Tasks in Project
Professional, will this data apss through to Project Server Database on
update? I added the Text1 field on the time sheet, but the data is empty in
Text1 field.
 
G

Gary L. Chefetz [MVP]

Diane:

If you want the custom field name to appear in Project Web Access, you
should use an Enterprise field. Local field customizations are local to the
project they're created in. You can, however, add a standard text field to
the timesheet, however it will not carry a custom name into Project Web
Access. Adding a field (standard or enterprise) to the time sheet requires
several steps.

1) Customize the field
2) In your project, go to Tools > Customize > Published fields and add the
field to your project
3) Logon to Project Web Access and customize the timesheet view to include
the new custom field
4) Republish your project to push the information to PWA

--


Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

For Project Server FAQs visit
http://www.projectserverexperts.com

For Project FAQs visit
http://www.mvps.org/project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top