Seb@stien
In the PWA 2003 timesheet, I show the columns "Real end date" and "%work
complete".
Resources connect to PWA and when the task is over, they put 100% in the
"%work complete" column and put the new end date of the task in the "real
end date".
For example : when the task has last 3 days more than initialy planned by
the project manager.
Then the project manager accepts the tasks updates and it makes MSP update
the planning with the correct dates. The tasks are shown as complete in MSP.
But, in the PWA timesheet, the resource can see his old task again, with
%work complete = 73% !!! And not 100% !
Can somebody explain me why ?
Does it come from the configuration of Project Server ?
I noticed that it does not occur if the resource does not fill the "real end
date" field. The task remains at 100% after the acceptation of the project
manager.
Thanks for help
Seb@stien
complete".
Resources connect to PWA and when the task is over, they put 100% in the
"%work complete" column and put the new end date of the task in the "real
end date".
For example : when the task has last 3 days more than initialy planned by
the project manager.
Then the project manager accepts the tasks updates and it makes MSP update
the planning with the correct dates. The tasks are shown as complete in MSP.
But, in the PWA timesheet, the resource can see his old task again, with
%work complete = 73% !!! And not 100% !
Can somebody explain me why ?
Does it come from the configuration of Project Server ?
I noticed that it does not occur if the resource does not fill the "real end
date" field. The task remains at 100% after the acceptation of the project
manager.
Thanks for help
Seb@stien