What does the "All tasks updated into project" option filter out on the
Updates tab? I would think that it would show task information that has
already been updated into the project plan; however, when I update certain
tasks in the project plan and then filter using this option I can see nothing.

Thanks!
 
R

Reid McTaggart

If you have accepted updates via PWA, processed them using the Update button,
and saved the updated project, then this filter will display those tasks that
have been updated.

So, to answer your question, that selection filters out everything except
tasks that have been updated into project, just as its name implies.
 