Filtering Assignment rows in Resource Usage View

S

Stéphane

Hi,
I have a problem with the resource Usage View. I cannot manage to filter out
Assignment rows. Either using a regular or automatic filter, only the nodes
(resources) are filtered, but not the leaves (assignments). My filter is
basically : Remaining Work "does not equal" 0.
What can I do ?
 
D

Dale Howard [MVP]

Stephane --

What version of Microsoft Office Project are you using? 2003 or 2007? If
you are using 2007, have you tried the Work Incomplete filter instead? In
2007, that filters out all task assignments that are completed (where
Remaining Work = 0 hours)? Let us know.
 
D

Dale Howard [MVP]

Stephane --

I'm not sure whether it's a known problem. So, please answer my original
question: Have you tried the Work Incomplete filter? If so, does it work?
If not, then I suspect you are seeing a limitation of the 2003 version.
 
S

Stéphane

Correct, it seems to work. Unfortunately if you open again an assignment
level, you're dead, you have to reapply the filter every time.
Thanks.
 
Top