Filtering complete activites on timesheets

L

lawj

Unfortunately we are not ready to roll out PWA so we need to use manual timesheets at present (modified Resource Usage view). I would really like to filter completed activities from the timesheet but as far as I can tell there is no way to differentiate between activities which really are finished (ie zero estimates left) and activites which are not actually finished but need to be re-estimated.

Can someone help?
 
D

Dale Howard [MVP]

lawj --

Until you begin using PWA, in which your team members can adjust the
Remaining Work values on tasks, you will need to make this a training and
performance issue with your team members when they report progress. Ask
them to indicate which tasks are truly complete and which tasks have
additional Remaining Work, and then ask them how much Rem. Work is left.
Adjust the Remaining Work on any task assignments and then apply the Work
Incomplete filter. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"


lawj said:
Unfortunately we are not ready to roll out PWA so we need to use manual
timesheets at present (modified Resource Usage view). I would really like
to filter completed activities from the timesheet but as far as I can tell
there is no way to differentiate between activities which really are
finished (ie zero estimates left) and activites which are not actually
finished but need to be re-estimated.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top