I am using the resource usage view (within my resource pool) to view my
percentage allocation of my resource. The timescales at the top start at Nov
08, but I want to start the view from Jun 09. How can I do this?, I have
tried to use the date range filter and looked at one or two filters but they
dont seem to do anything, presumably because I had tasks that started in Nov
08.