Filtering timescale dates on resource usage view

D

ddrjbrown

I am using the resource usage view (within my resource pool) to view my
percentage allocation of my resource. The timescales at the top start at Nov
08, but I want to start the view from Jun 09. How can I do this?, I have
tried to use the date range filter and looked at one or two filters but they
dont seem to do anything, presumably because I had tasks that started in Nov
08.
 
J

JulieS

Hi ddrjbrown,

Filtering does not remove any data from the timescale, it will
merely hide those assignments which fall out of the date range you
requested, but a user can still scroll the timescale (right side) to
see any date range they wish.

You may get a better understanding of what the Date Range filter
does it you apply it as a highlight filter first to see which
assignments meet the criteria (and would be visible in a regular
filter) and which assignments would be hidden.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top