In Web access task view, I would like the people in my team to see only
tasks where the remaining work is not null. (meaning 2 or 3 tasks a week
instead of the tens of tasks they worked on the past months). I can do that
with a Custom filter, but is there a way to have this filter activated by
default ? The reporting view doesn't seem to be that customizable (I could
only add or remove columns, but not attach a filter). Is there a way to do
this ?
 
S

Stéphane

Do you know if this was improved in 2007 ?
Is there any way to suggest this ER for a later version ?
 
D

Dale Howard [MVP]

Stephane --

Have you asked your team members to click the Current Tasks link in the
sidepane on the left? That will hide all completed tasks, and will show
only those tasks that should have started but have not, those tasks that are
in-progress, and tasks that begin in the next 10 days. Just a thought.
Hope this helps.
 
C

crook

Hi Stephane,

Ask your PMs to ensure tasks with 0d remaining are 100% complete (and
100% work complete) in MS Project Pro, then republish the tasks. You
may have to tick the "Overwrite actual work entered by resources"
checkbox. This will force the tasks to be "Completed" in PWA and will
drop off the current tasks view.

HTH,
Crook
 