Dear Friends, How do I find out what tasks should be complete next week? Thanks, Prashanth
P prashanth.sharangapani May 21, 2009 #1 Dear Friends, How do I find out what tasks should be complete next week? Thanks, Prashanth
J Jan De Messemaeker May 21, 2009 #2 Hi, Activate the auto filter On the finish field use Custom.. Use "Is greater than or equal to" ... (next monday) AND "Is less that or equal to" ... (friday next week) instead of (monday next week) and (friday next week) use the dates. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf
Hi, Activate the auto filter On the finish field use Custom.. Use "Is greater than or equal to" ... (next monday) AND "Is less that or equal to" ... (friday next week) instead of (monday next week) and (friday next week) use the dates. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf