A
Ana Figueira
I'm using MS Project 2007 and I'm having an issue on how it is calculation
"Finish Dates" for the tasks.
1. I have set the work hours per day for the project in the “working timeâ€
at 6.5 hours per day and 32.5 hours per week. I have also set the default
start and end time to total 6.5 hours/day (10:00 AM - 4:30 AM). I'm using the
standard calendar which has weekend as 'non-working" days.
2. For example, I have a task that is 80 work. I'm assigning one resource to
the task. MSProject correctly calculates “Duration†for that task (at 6.5
hours/day) at 12.31 working days.
3. That task start date is 7/2/09. If "Duration" is 12.31 working days, the
"Finish Date" should be Monday 7/20/09, but instead it calculating the Finish
Date to be 7/16/09. It is basically using the 6.5 hour/day to calculate
Duration but ignoring to calculate Finish Date.
Does anyone know why?
I understand that resources can be allocated individually at a lesser
velocity (i.e. 80%) but I'd like to know why is MS Project not calculating
Finish Date correctly with my settings.
Any help would be greatly appreciated!!
Regards,
Ana
"Finish Dates" for the tasks.
1. I have set the work hours per day for the project in the “working timeâ€
at 6.5 hours per day and 32.5 hours per week. I have also set the default
start and end time to total 6.5 hours/day (10:00 AM - 4:30 AM). I'm using the
standard calendar which has weekend as 'non-working" days.
2. For example, I have a task that is 80 work. I'm assigning one resource to
the task. MSProject correctly calculates “Duration†for that task (at 6.5
hours/day) at 12.31 working days.
3. That task start date is 7/2/09. If "Duration" is 12.31 working days, the
"Finish Date" should be Monday 7/20/09, but instead it calculating the Finish
Date to be 7/16/09. It is basically using the 6.5 hour/day to calculate
Duration but ignoring to calculate Finish Date.
Does anyone know why?
I understand that resources can be allocated individually at a lesser
velocity (i.e. 80%) but I'd like to know why is MS Project not calculating
Finish Date correctly with my settings.
Any help would be greatly appreciated!!
Regards,
Ana