Is there any way to have resources change their Finish Date in PWA?
Right now we have the ability for resources to enter actual hours and
remaining hours, or percent complete for each task.
But there is a need on one project to not go this level of detail and have
the resources account for every hour, but for the resources
to just be able to go into PWA and modify the start and finish dates for
tasks they are assigned.
Currently we know of no way to make the Finish Date field a field that the
user can adjust through PWA.
Thanks,
Bill
Right now we have the ability for resources to enter actual hours and
remaining hours, or percent complete for each task.
But there is a need on one project to not go this level of detail and have
the resources account for every hour, but for the resources
to just be able to go into PWA and modify the start and finish dates for
tasks they are assigned.
Currently we know of no way to make the Finish Date field a field that the
user can adjust through PWA.
Thanks,
Bill