Murthy
I have a fixed units, effort driven task, where I have defined the duration
as 7 days. Assigned two resources. It does show the work correctly as 112
hours, however finish date&time shows as task ending at 2pm, instead of 6pm.
As a result the next FS task is starting at 2pm. What could be the reason.
Strategy Finalization 112 hrs 7 days Mon 9/21/09 8:00 AM Tue 9/29/09 2:00
PM Resource A, Rsource B.
Calendar settings as below:
Tools/Change working time: Non Default time was selectied; 8:00am to 12:00
and 1:00 to 5:00. Under options I see default time is 8:00 to 6:00, and hours
per week as 45, hours per day as 8, and days per month as 20.
(This task is from a project plan I have received for my review).
Thanks
Murthy
as 7 days. Assigned two resources. It does show the work correctly as 112
hours, however finish date&time shows as task ending at 2pm, instead of 6pm.
As a result the next FS task is starting at 2pm. What could be the reason.
Strategy Finalization 112 hrs 7 days Mon 9/21/09 8:00 AM Tue 9/29/09 2:00
PM Resource A, Rsource B.
Calendar settings as below:
Tools/Change working time: Non Default time was selectied; 8:00am to 12:00
and 1:00 to 5:00. Under options I see default time is 8:00 to 6:00, and hours
per week as 45, hours per day as 8, and days per month as 20.
(This task is from a project plan I have received for my review).
Thanks
Murthy