Finished task still appeared in PWA

A

Alain

Hello,

With Project Server 2003, in PWA, when we hide a task, even if the reaming
work = 0 and the finish date is smaller than today, The hidden tasks, keep
showing up in the PWA the next day....

Any suggestion ? Thanks.
 
D

Dale Howard [MVP]

Alain --

This happens if the manager of the project clicks Collaborate - Publish -
Republish Assignments. I think the manager needs to begin using
Collaborate - Publish - All Information instead. Hope this helps.
 
Top