Fiscal Year and Calendars in MSP2003

J

Jim Puls

It appears that there can be only one fiscal year in MSP2003. If I
create two calendars, for example, Home Office with a 4/1 to 3/31 FY,
and North America with a 1/1 to 12/31 FY, the fiscal year I enter last
seems to apply to all calendars. Is this correct or am I missing
something here?

Thanks,

Jim Puls
Sentinel Technologies
 
D

Dale Howard

Jim --

The fiscal year option is applied on a project by project basis in Microsoft
Project . As you have probably discovered, this option is set by clicking
Tools - Options - Calendar, and then selecting the "Fiscal Year Starts In"
option. Because of this, you should only need to create one company
calendar in the Enterprise Global. This calendar would simply show your
company's holidays as non-working time. You can then apply the appropriate
Fiscal Year settings in each project individually. Hope this helps.
 
J

Jim Puls

Thanks, Dale!

Dale Howard said:
Jim --

The fiscal year option is applied on a project by project basis in Microsoft
Project . As you have probably discovered, this option is set by clicking
Tools - Options - Calendar, and then selecting the "Fiscal Year Starts In"
option. Because of this, you should only need to create one company
calendar in the Enterprise Global. This calendar would simply show your
company's holidays as non-working time. You can then apply the appropriate
Fiscal Year settings in each project individually. Hope this helps.
 