Hi there! I am deploying Project Server 2003 and have run into an
issue. The company I'm deploying for uses a fiscal calendar starting
the beginning of November. I have opened the Enterprise Global and
edited the standard calendar to begin the fiscal year in November. But
it isn't carrying over when I create a new project. Is there something
additional I need to do to ensure that all projects use a fiscal
calendar beginning in November?
Sincerely,
Gary