Hi,
I am using Project 2007 and have allocated a fixed cost to individual
task. On eof the task is flowing in two financial years and this fixed
cost is now showing in both the financial years.
I have tried to change the accrual method from Start to Finish to
Prorated, however, it does not change the report I am looking through.
I am refering the report available at Report > Reports > Costs >
Budget.
Please advise.
Kishore