fixed costs are not included in PV in MSPROJECT 2007

K

Konstantinos

Dear all,

When you want to use the EV in MS Project 2007 having both fixed costs and
resource costs, this is what happens:
The BCWS (=PV) is calculated in the Earned Value Table including both fixed
costs and resource costs. However, when you go for "Visual Reports">"Earned
Value" the Planned Value (PV) displayed gives only resource costs and ignores
fixed costs.

Any ideas?
 