Grant 702
I am trying to figure out how I can reflect equipment costs at a task line
item in addition to standard resource costs. An example would be:
Material: Bitumen
Units: 3
Quantity Type: Cubic metres
Total: xxxx
The quantity type will change depending on the material used. My initial
thoughts are to create a separate costs table filtered on Capex items at a
task level and enter in custom fields for Quantity Type and Total (formula to
calculate). The concern I have is the cost rollup will be lost in summary
reporting. Can someone please help with an approach that might work in this
instance.
Best Regards
item in addition to standard resource costs. An example would be:
Material: Bitumen
Units: 3
Quantity Type: Cubic metres
Total: xxxx
The quantity type will change depending on the material used. My initial
thoughts are to create a separate costs table filtered on Capex items at a
task level and enter in custom fields for Quantity Type and Total (formula to
calculate). The concern I have is the cost rollup will be lost in summary
reporting. Can someone please help with an approach that might work in this
instance.
Best Regards