K
Kevin Flanagan
I understand there are issues with getting fixed costs to
show in Project Center Views, but when trying to repeat
behavior of projects with fixed costs, I can't. I have a
project that has almost 1.5MM of fixed costs in it
assigned to tasks (all tasks are at zero duration). When
the plan was published it pulled in the one task that had
$245,000 but the tasks that had either $50K or $99K were
not picked up in the OLAP cube Portfolio Analyzer View
Totals. Why did it pick up the one task and not the
other 20? Of the ones it did not pick up some have
resources assigned and others do not. Any help would be
greatly appreciated.
Kevin
show in Project Center Views, but when trying to repeat
behavior of projects with fixed costs, I can't. I have a
project that has almost 1.5MM of fixed costs in it
assigned to tasks (all tasks are at zero duration). When
the plan was published it pulled in the one task that had
$245,000 but the tasks that had either $50K or $99K were
not picked up in the OLAP cube Portfolio Analyzer View
Totals. Why did it pick up the one task and not the
other 20? Of the ones it did not pick up some have
resources assigned and others do not. Any help would be
greatly appreciated.
Kevin