D
Demir Ozkaya
I have two questions:
1..Nonworking time is defined for a resource in the resource calendar.
Same resource is assigned to a fixed duration task.
If the task starts at the nonworking time of the resource, no warning
is given, task start time does not change, task duration does not
change, no overallocation is shown. If you are careful enough, you
find out from the work field, the resource does not work in the assigned
task. If you do not control the work field, you will assume that there is
no problem with the project plan.
Is this a bug or am I doing something wrong ?
2..Manual modification of the task baseline values makes it very
unreliable. Is there any way to stop manual modification of baseline
values ?
I will appreciate if someone could help.
Demir
1..Nonworking time is defined for a resource in the resource calendar.
Same resource is assigned to a fixed duration task.
If the task starts at the nonworking time of the resource, no warning
is given, task start time does not change, task duration does not
change, no overallocation is shown. If you are careful enough, you
find out from the work field, the resource does not work in the assigned
task. If you do not control the work field, you will assume that there is
no problem with the project plan.
Is this a bug or am I doing something wrong ?
2..Manual modification of the task baseline values makes it very
unreliable. Is there any way to stop manual modification of baseline
values ?
I will appreciate if someone could help.
Demir