I have my default task type set to fixed duration.
I have a task with say a duration of 2 days with 1 person assigned to it. If
I add another resource and ask Project to reduce the duration (using the
smart tag option) I expect it to halve the duration. Sometimes it does,
other times it doesn't. I have tried ticking the effort driven check box and
sometimes it even increases the duration! What's going on?
If I fix Duration, then why is it changing?
Thanks (Project XP user)