M
MSeppola
Hi,
I have 47 Fixed Duration tasks that take 2 hours to complete. Each task
must be completed before the next task can be started, and must be completed
the day it is started. The work day is 7.5 hours. I can complete 3 tasks
per day. Project 2007 is starting a 4th task and finishing it on the next
day. Can I set up tasks in Project to complete the day, or shift, they are
started and move the 4th task to the next day?
I have 47 Fixed Duration tasks that take 2 hours to complete. Each task
must be completed before the next task can be started, and must be completed
the day it is started. The work day is 7.5 hours. I can complete 3 tasks
per day. Project 2007 is starting a 4th task and finishing it on the next
day. Can I set up tasks in Project to complete the day, or shift, they are
started and move the 4th task to the next day?