"Fixed Duration" Tasks

M

MSeppola

Hi,

I have 47 Fixed Duration tasks that take 2 hours to complete. Each task
must be completed before the next task can be started, and must be completed
the day it is started. The work day is 7.5 hours. I can complete 3 tasks
per day. Project 2007 is starting a 4th task and finishing it on the next
day. Can I set up tasks in Project to complete the day, or shift, they are
started and move the 4th task to the next day?
 
D

Darrell

Starting with the fourth task in the squence you could add 1.5hrs of lag to
move the forth task to the next day and then apply the lag to every third
task there after. You would have to manually adjust if things did not go
according to plan, or perpahs you could write a macro to compare the start
and finish dates and if there is a delta automatically add the lag?

Just my two cents worth,
Darrell
 