A
ayus
Hi Guys,
How do i setup a resource to do a task for 8 hours but over 5 days.
Thanks
Ayowole
How do i setup a resource to do a task for 8 hours but over 5 days.
Thanks
Ayowole
Hi Guys,
How do i setup a resource to do a task for 8 hours but over 5 days.
Thanks
Ayowole
1. Create the task
2. Set task type to fixed duration and set duration to 5 days
3. Set dependencies (if necessary)
4. Add the resource with 20% assignment units (assuming your resource
works 40 hrs/week)
To get to the right assignment units percentage, you need to divide
the work you want to assign (in your case 8 hours) by the total number
of hours that the resource would normally work over this period (5
days times 8 hours a day equals 40 hours).
Thanks. It actually solved my problem- Tekst uit oorspronkelijk bericht niet weergeven -
- Tekst uit oorspronkelijk bericht weergeven -