Fixed Units

R

Ryan

I need to make sure that some resources are fixed to 5 hrs
a day to a certain project, task. I have created a task
and said 63% fixed units are what they are assigned to
every day. Now, how does this handle statusing of the
project?
thx
ry
 
G

Gary L. Chefetz

Ryan:

Try restating the question. I'm not sure what you're asking and the lack of
replies indicates that nobody else seems to be connecting with it either.

--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 
R

ryan

its like this: 5 hrs i want dedicated everyday to a
resource till the end of the year. now no matter what they
put down every day the next day(s) is 5 hrs. Fixed
duration redistributes the work and fixed work pushes it
to the end, i don't want that.
thx
r
 