D
David
I am struggling with Fixed Work. We are seeing recalculations of
duration where we are not expecting. For example, I have a project
that has a task that has 45 hours of work (9 hour calendar day), it
starts on Monday and ends on Friday, a Must Finish On Constraint, Fixed
Work, and one resource at 100%. In this particular example, Actual
Work of 2 hours was entered from a timesheet one week before the task
was scheduled to start. The end result in the Gantt view shows
duration of 52 hours and not 45 hours with are remaining work of 43
hours. The Task Usage view shows the duration with 45 hours and 43
hours remaining. Any ideas why the two views would be different? Our
PM group uses the Gantt view and the resource managers and accounting
groups use the Task Usage view causing some confusion.
We are running Project Pro 2003, with SP2.
Thanks.
duration where we are not expecting. For example, I have a project
that has a task that has 45 hours of work (9 hour calendar day), it
starts on Monday and ends on Friday, a Must Finish On Constraint, Fixed
Work, and one resource at 100%. In this particular example, Actual
Work of 2 hours was entered from a timesheet one week before the task
was scheduled to start. The end result in the Gantt view shows
duration of 52 hours and not 45 hours with are remaining work of 43
hours. The Task Usage view shows the duration with 45 hours and 43
hours remaining. Any ideas why the two views would be different? Our
PM group uses the Gantt view and the resource managers and accounting
groups use the Task Usage view causing some confusion.
We are running Project Pro 2003, with SP2.
Thanks.