Fixing Schedule

R

Robin Roe

Hi

Is there any wak of fixing the weekly work hours and duration on a task
regardless of what actual hours have been entered for previous weeks on that
task.

Example
Task 1 has a duration of 4 weeks.
Resource A is assigned for 40 hrs for the task (2 hrs per day)
Resource A enters 8 Hrs for week 1 (10 hrs expected)

Results -

With fixed Duration - All future days are now at 2.13hrs
With Fixed Units - Has extended task by one day
With Fixed Work - Has extended task by one day

This is what I would have expected, but is there a way to keep all future
hrs and duration as planned rather than project automatically recalculating
this for me?

Thanks
 
D

Dale Howard [MVP]

Robin --

You can only fix one of three variables in the Duration equation. You can
fix Units, Work, or Duration, but not two of them. Therefore, I would
recommend you make the task a Fixed Duration task and live with the hours
changing. Hope this helps.
 
R

Robin Roe

Thanks Dale,
--
Robin


Dale Howard said:
Robin --

You can only fix one of three variables in the Duration equation. You can
fix Units, Work, or Duration, but not two of them. Therefore, I would
recommend you make the task a Fixed Duration task and live with the hours
changing. Hope this helps.
 