I have used Flag1 in my mpp file to indicate if a task is completed or
not. This allows the task assignee to explicitly indicate if he has
completed a task or not, instead of filling in 0 for the remaining
hours. The following happens:
- The task assignee sees the Flag1 field in his timesheet and is able
to set the Flag1 value to Yes
- The project manager can see that the Flag1 field has been set to Yes
when he updates project progress within MS Project Pro
However when the PWA view has been closed, the project manager doesn't
see that the Flag1 has been updated.
What needs to be done to update the Flag1 field with the latest
information???
not. This allows the task assignee to explicitly indicate if he has
completed a task or not, instead of filling in 0 for the remaining
hours. The following happens:
- The task assignee sees the Flag1 field in his timesheet and is able
to set the Flag1 value to Yes
- The project manager can see that the Flag1 field has been set to Yes
when he updates project progress within MS Project Pro
However when the PWA view has been closed, the project manager doesn't
see that the Flag1 has been updated.
What needs to be done to update the Flag1 field with the latest
information???