How do I put into the schedule the number of hours that I have available for
a piece of equipment - like a forklift. I understand that "material" type of
resource exists but this is a little different in that it isn't consumable.
It has to be a set number of hours available per day - regardless if 1
Forklift driver or 30 are available - the forklift itself isn't available any
more (or less) hours per day. Also, this is something I want to track in
hours so that I can lump it in with other, human, resources. How can I track
the number of hours that it is available?
a piece of equipment - like a forklift. I understand that "material" type of
resource exists but this is a little different in that it isn't consumable.
It has to be a set number of hours available per day - regardless if 1
Forklift driver or 30 are available - the forklift itself isn't available any
more (or less) hours per day. Also, this is something I want to track in
hours so that I can lump it in with other, human, resources. How can I track
the number of hours that it is available?